THE Metropolitan Manila Development Authority (MMDA) has proposed the construction of rainwater impounding facilities inside Camp Aguinaldo to ease recurring flooding on EDSA, with the proposed design released on Wednesday, Aug. 27.
The plan requires detention ponds that will temporarily store excess rainwater during downpours and gradually release it into the EDSA drainage system, leading to the Makiling Creek.
As proposed, the project will be implemented in three phases, covering 182 hectares and involving a golf course near Gate 2, another near Gates 3 and 4, and an open space near Gate 6.
For the first phase near Gate 2, the detention pond has a 361-meter perimeter, a 4,650-square-meter area, an 8-meter depth, and a 37,200-cubic-meter capacity, designed for a 25-year return period (15.6 mm per hour over 24 hours), exceeding the needed 36,945 cubic meters.
MMDA’s schematic shows that under normal weather, the water bypasses the pond and flows through the lagoon to EDSA.

During heavy rain, floodgates divert water flow into the pond; after rain, pumps discharge stored water slowly into EDSA toward the Makiling Creek.
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
The scope of works covers the impounding area, operations and powerhouse, drainage and electromechanical works, and landscaping and golf course restoration, with a treatment facility under consideration., This news data comes from:http://nreip.yamato-syokunin.com
Officials said operations and maintenance arrangements, and a memorandum of agreement, are still under discussion.
- 25 countries suspend postal services to US over tariffs – UN
- Former Bulacan district engineer admits going to casinos
- Israeli strikes in Yemen's capital kill six, Houthis say
- India's Modi meets Japan's Ishiba as he begins Asia tour
- Pagasa: Rainy Monday over Visayas, Luzon areas due to LPA, 'habagat'
- Filipino fulfills dream of performing with K-pop group before home fans
- DSWD program reduced hunger
- Thai opposition holds kingmaking summit deciding new PM
- Manila Water announces service disruption for over 12K households in Mandaluyong due to leak repair
- PH to see ‘blood moon’ Sept. 7-8